What has changed
What changed in the legal, funding and residents' rights statements on this site, with the source each change was checked against and the date.
On this page
The timeline
18 changes between 9 October 2026 and 26 October 2026, newest last.
Changes to statements
Who is responsible for work a building needs, and who the cladding protection is for
- Was
- If work is needed, funding routes may apply, and many qualifying leaseholders are protected from the cost of cladding remediation.
- Now
- If work is needed, the owner of the building is responsible for it, and government funding routes may apply. Many qualifying leaseholders are protected from the cost of cladding remediation (Building Safety Act 2022 s.122 and Schedule 8 para 8).
- Source
- Building Safety Act 2022, section 122 and Schedule 8 para 8 (read on 26 October 2026)
- Pages
- /faqs
Whether the Cladding Safety Scheme funds buildings over 18 metres in London
- Was
- It does not fund private buildings over 18 metres in London.
- Now
- Since 1 September 2025 it is the one route for new applications to fund unsafe cladding on residential buildings over 11 metres in England, London included: Homes England takes every new application for government remediation funding in England.
- Source
- Cladding Safety Scheme overview, GOV.UK, updated 21 October 2026 (read on 22 October 2026)
Whether the Remediation Bill has been introduced
- Was
- The Building Safety (Remediation of Unsafe Cladding etc) Bill was shown as not yet introduced.
- Now
- GOV.UK published a guide to the Building Safety (Remediation of Unsafe Cladding etc) Bill on 14 October 2026. The funding page now says the duty is not yet law and links to that guide. The Building Safety Levy card was removed.
- Source
- GOV.UK, Guide to the Building Safety (Remediation of Unsafe Cladding etc) Bill, published 14 October 2026 (read on 26 October 2026)
- Pages
- /funding
Who the Building Safety Regulator is
- Was
- It introduces a new regulatory framework for higher-risk buildings, creates the Building Safety Regulator (BSR) as part of the Health and Safety Executive, and establishes new roles and responsibilities for those involved in the design, construction, and management of buildings.
- Now
- The regulator named in Part 2 of the Act. Since 27 January 2026 the Act names it as "the Building Safety Regulator" (s.2(1), as substituted by SI 2026/20).
- Source
- Building Safety Act 2022, section 2(1), as substituted by SI 2026/20 (read on 21 October 2026)
Who enforces the Fire Safety Order
- Was
- The fire and rescue authority enforces the RRO in most premises; the BSR enforces it in higher-risk buildings.
- Now
- It is enforced by your fire and rescue authority (art. 25). Article 25 does not name the Building Safety Regulator. The penalty is stated once, on the guide's Penalties section.
- Source
- Regulatory Reform (Fire Safety) Order 2005, article 25 (read on 21 October 2026)
What the EWS1 ratings mean, and how long a form lasts
- Was
- A2: Combustible materials present but in limited quantity. A3: Combustible materials present. Remediation or mitigation works are required to meet fire safety standards. The assessment results in a completed EWS1 form which is valid for 5 years from the date of assessment.
- Now
- Option A (A1, A2, A3) where the wall materials are unlikely to support combustion, and option B (B1, B2) where they may; B2 means remedial works are needed. RICS says the form is "NOT a life safety certificate". The five-year statement is removed.
- Source
- RICS, EWS1 form, 3rd edition (16 March 2022), and RICS external wall system FAQs (dated 16 June 2026) (read on 21 October 2026)
- Pages
- /legislation/ews1
Which edition of PAS 9980 applies to a fire risk appraisal of the external walls
- Was
- PAS 9980:2022 and the FRAEW. PAS 9980:2022 is the publicly available specification published by BSI that sets out a methodology for the Fire Risk Appraisal of External Walls (FRAEW) of existing multi-storey residential buildings.
- Now
- External wall appraisals (FRAEW). PAS 9980:2026 is the current edition, published by BSI in September 2026. It replaced PAS 9980:2022, which was superseded on 11 September 2026. Appraisals competently produced under the 2022 edition remain valid. The guide moved from /legislation/pas-9980 to /legislation/external-wall-appraisals, and other pages now say fire risk appraisal of the external walls (FRAEW).
Building assessment certificates
- Was
- Buildings cannot be legally occupied without this certificate (with transitional provisions for existing buildings).
- Now
- It is an offence to occupy a higher-risk building that is not registered (section 77). The principal accountable person must apply for a building assessment certificate within 28 days of a direction from the Building Safety Regulator (section 79). There is no offence of occupying a registered building that has not yet been certified.
- Source
- Building Safety Act 2022, sections 77 and 79 (read on 14 October 2026)
Key dates for registering higher-risk buildings
- Was
- 1 October 2023: Registration of existing higher-risk buildings opens. 1 April 2024: Duty to apply for Building Assessment Certificates begins.
- Now
- April 2023: registration of existing higher-risk buildings opens (the Building Safety Regulator's guidance was published on 12 April 2023). 1 October 2023: it becomes an offence to occupy an unregistered higher-risk building (section 77, brought into force by SI 2023/993). 16 January 2024: section 79 in force; the regulator can direct the principal accountable person to apply for a building assessment certificate within 28 days.
Which Fire Safety (England) Regulations 2022 duties apply at which height
- Was
- Buildings over 11 metres must provide external wall information, floor plans, wayfinding signage and lift information; buildings at or above 18 metres must have evacuation plans, PEEPs, fire door checks and monthly lift checks.
- Now
- External wall design and materials (regulation 5), floor plans (regulation 6), lifts and firefighting equipment checks (regulation 7), wayfinding signage (regulation 8) and the secure information box (regulation 4) apply to high-rise residential buildings: at least 18 metres or seven storeys with two or more sets of domestic premises (regulation 3). Fire door checks (regulation 10) apply above 11 metres. Fire safety instructions and fire door information (regulations 9 and 10) apply to every building with two or more sets of domestic premises. Evacuation plans come from the Fire Safety (Residential Evacuation Plans) (England) Regulations 2025, in force 6 April 2026, not from the 2022 Regulations.
What applies to a residential building over 11 metres
- Was
- Buildings over 11 metres require external wall assessments under the Fire Safety Regulations 2022.
- Now
- A residential building at least 11 metres high (or with at least five storeys) and two or more homes is a relevant building under Part 5 of the Building Safety Act 2022 (section 117), which brings in the leaseholder cost protections (Schedule 8, through section 122) and remediation orders (section 123). Above 11 metres the responsible person must check its fire doors under regulation 10 of the Fire Safety (England) Regulations 2022. The external wall record under regulation 5 applies at 18 metres or seven storeys.
Where our building heights come from
- Was
- MatchKey's building height analysis uses LiDAR data to measure building heights.
- Now
- MatchKey's building height analysis uses Ordnance Survey building height data, read to the top storey as the law measures it. Owners can confirm or correct the height in the questionnaire.
Source links that had moved or been removed
- Was
- Ten source links pointed at pages that now return 404 or redirect elsewhere: the EWS1 page on rics.org, the Responsible Actors Scheme guidance, the Social Sector ACM fund guidance, the Building Remediation Hub guidance (also cited as the Responsible Entity source), the National Remediation Service, the golden thread guidance, the BSI PAS 9980 and PAS 79-2 pages, and the high-rise register guidance.
- Now
- Each link points at the current primary page: the developer remediation contract publication, the Social Sector ACM fund application guidance (closed to new applications on 1 September 2025), the Cladding Safety Scheme application guidance for the Hub, the Remediation Acceleration Plan update (which names the National Remediation System, since renamed the National Remediation Database), the Building Safety Regulator's golden thread guidance, BSI Knowledge for both PAS documents, the RICS external wall system FAQ, and GOV.UK's register or manage a high-rise residential building page.
- Source
- Each page fetched and read on 14 October 2026 (HTTP 200, GOV.UK content API where the page is on GOV.UK) (read on 14 October 2026)
Developer remediation contract guidance updated on GOV.UK
- Was
- Checked against GOV.UK on 8 October 2026.
- Now
- GOV.UK added "Developer remediation contract: guidance for local regulators" on 12 October 2026. The page was re-read on 14 October 2026; the facts on this site did not change.
- Source
- GOV.UK, Developer remediation contract (collection), change history 12 October 2026 (read on 14 October 2026)
How often the sources are checked
- Was
- Pages are reviewed at least every six months.
- Now
- Every source is fetched automatically each week. A source that changes, moves or disappears freezes the checked-on date shown on the site until a person has re-read it, and the change is listed here. At the time the page also said that nobody signs the facts off; since 21 October 2026 a person re-reads any source that changes. Owners can give evidence where their data differs. Fire safety law is enforced by the fire and rescue authority (Regulatory Reform (Fire Safety) Order 2005, article 25), and the Building Safety Regulator enforces the Building Safety Act 2022 duties for higher-risk buildings.
- Source
- Golden Ledger's weekly source check (read on 14 October 2026)
- Pages
- /legislation/funding
Which funding routes are open
- Was
- Six government remediation schemes; five open; most owners qualify for one. The Medium-Rise Scheme and the Waking Watch Replacement Fund listed as open.
- Now
- Since 1 September 2025 the Cladding Safety Scheme is the one open route for cladding funding on buildings over 11 metres; the Interim Measures Alarm Fund pays for interim alarms. The Building Safety Fund and the ACM funds closed to new applications on 1 September 2025; the Waking Watch Replacement Fund closed on 31 March 2026. The Medium-Rise Scheme was the Cladding Safety Scheme pilot, not a separate scheme.
- Source
- GOV.UK, Cladding Safety Scheme overview (updated 10 July 2026) and Interim Measures Alarm Fund guidance (read on 8 October 2026)
The name of the 11 to 18 metre band
- Was
- Buildings between 11m and 18m are classified as "High Risk".
- Now
- "High Risk" is not a term the law uses. A residential building at least 11 metres high (or with at least five storeys) and two or more homes is a relevant building under Part 5 of the Building Safety Act 2022 (section 117), and above 11 metres its fire doors must be checked under the Fire Safety (England) Regulations 2022; a building of 18 metres or seven storeys is a higher-risk building under section 65.
- Source
- Building Safety Act 2022, sections 65 and 117 (read on 8 October 2026)
- Pages
- /faqs
The instrument behind Key Building Information
- Was
- The Higher-Risk Buildings (Key Building Information etc.) (England) Regulations 2024.
- Now
- The Higher-Risk Buildings (Key Building Information etc.) (England) Regulations 2023 (SI 2023/396). The old /legislation/kbi-regs-2024 address redirects.
- Source
- SI 2023/396 (read on 9 October 2026)
Automated source checks
Once a week we fetch every law, regulation, standard, scheme and register page we cite and compare it with what we read last time. A person re-reads any source that changes. Until then it keeps the date a person last read it, and the change is then listed above.
Latest weekly check, 22 October 2026: 23 sources checked, 16 unchanged and 7 waiting for a person to re-read them. Each guide shows the date a person last read its sources, so that date is the one to rely on.
Last run . 23 sources checked.
| Source | Result | Source updated | Note |
|---|---|---|---|
| Building Safety Act 2022 | Changed since our review | not stated | |
| The Golden Thread | Unchanged | 18 September 2024 | Mention of safety case guidance removed and users pointed to 'Preparing a safety case report' guidance instead. |
| Principal Accountable Person (PAP) | Changed since our review | not stated | |
| Responsible Entity | Changed since our review | 21 October 2026 | |
| EWS1: External Wall Fire Review | Unchanged | not stated | |
| External wall appraisals (FRAEW) | First check, no baseline yet | not stated | |
| Fire Safety Act 2021 & Regulations 2022 | Unchanged | not stated | |
| Higher-Risk Buildings (Descriptions and Supplementary Provisions) Regulations 2023 | Unchanged | not stated | |
| The Higher-Risk Buildings (Key Building Information etc.) (England) Regulations 2023 | Unchanged | not stated | |
| PAS 79-2:2020, Fire Risk Assessment for housing | Unchanged | not stated | |
| Building Remediation Hub | Changed since our review | 21 October 2026 | |
| Companies House | Unchanged | 14 October 2026 | |
| BSR Register of Higher-Risk Buildings | Unchanged | 4 April 2024 | First published. |
| National Remediation Service (NRS) | Unchanged | 11 June 2026 | |
| Regulator of Social Housing | Unchanged | 4 June 2026 | |
| Regulatory Reform (Fire Safety) Order 2005 | Changed since our review | not stated | |
| Building Safety Fund (legacy) | Unchanged | 1 September 2025 | Updated to reflect the closure of the Building Safety Fund to new applications. |
| Cladding Safety Scheme (CSS) | Changed since our review | 21 October 2026 | |
| Interim Measures Alarm Fund | Unchanged | 11 September 2026 | The 'Eligibility' section has been updated to include the number of dwellings a building must have to make it eligible for funding. |
| Medium-Rise Scheme | Unchanged | 30 November 2022 | First published. |
| Developer Remediation Contract & Responsible Actors Scheme | Unchanged | 12 October 2026 | Added Developer remediation contract: guidance for local regulators. |
| Social Sector ACM Cladding Remediation Fund | Unchanged | 1 September 2025 | Updated to reflect the closure of the Social Sector ACM Cladding Remediation Fund to new applications. |
| Waking Watch Replacement Fund 2023 | Unchanged | 11 April 2025 | Updated to reflect details of the Waking Watch Replacement Fund extension announced in the Remediation Acceleration Plan |